New Track Construction Nears Completion on Krishna Bhir
english.ratopati.com · Tue Sep 15 01:48:21 GMT 2026

Chitwan. The construction of a new track, which was immediately started after a landslide blocked the road completely at Krishnabhir along the Prithvi Highway, has reached the final stage. On Sunday, after completing the cutting of the cliff face and road leveling, some vehicles were allowed to pass as a test. After the test was successful, efforts are being intensified to operate regular vehicle traffic.
Engineer Ishwar Nepal of the construction company responsible for the new track construction said that the construction work has reached the final stage. According to him, graveling, slope cutting, and drain construction work are underway on the 11th day today.